Posted by on Aug 17, 2011 in Airport, North Central Airport | Airport | 0 comments

North Central Airport | Airport

This project generally consists of the reconstruction of Taxiway B including; reclaiming existing bituminous surface course with existing base course material, paving, pavement markings as well as lighting and signage improvements for approximately 5,000 feet x 50 feet of pavement.

Back to Projects Page
Rhode Island Airport Corporation
$2,496,602.50
The work also consists of the construction of2 new bypass taxiways at each end of Runway 5-23. Each new taxiway (B2 and B5) is approximately 275 feet x 50 feet and consists of a new full depth pavement section, markings, lighting, signing and drainage improvements. Work also consists of reconstructing the Airport’s On-Site Water Treatment System (OWTS)