Rhode Island Resource Recovery 
$7,100,000.00
Relocation / realignment of an existing 3,500 LF Brook.

60,000 CY of rock to blast and process.

810 LF precast concrete box culvert set in a 35’ rock cut.

Constructed two lined detention ponds.

Relocated / realigned a 3,000 foot access road.

Extensive wetland planting, wetland re-creation, and landscaping. Modifications to several existing detention ponds.